Having sung the praises of the guys doing the conservatory I am now getting fed up. Yesterday (Friday 31 August) the build was a whole week later than expected.
As you can see progress is being made
but I found out yesterday that because they are waiting for 4 panes of glass they won't be back until next Thursday! I reckon there's more than 2 days work left to get it finished so we're going to have to wait even longer before we can get plasterer, electrician, plumber and tiler in: And juggling these guys is hard enough as it is without having to put them off any more.
They've also royally pissed me off with the guttering - I was assured that the guttering would go all around to the side of the house so I could divert the water into a series of water butts. But, somebody mis-measured the roof so the main part will now have to go into a soak-away in the border. They did suggest we have it go straight into a water butt but, as you can see from the picture below, that butt would be right in front of the window (on the left of the picture) and once it was full it would still end up over-flowing into the border!
And if there was nothing there then we run the risk of flooding, both our border and next doors. So they will be digging a soak-away - what a waste (and possible mess while they destroy the border to dig the hole).
I wonder what other surprises they have in store for us? :(